this part of the project will not be impacted. Progress yesterday and
this morning is good and we are hoping to be finished re-surfacing by
the end of the day.
The last of the silt fence will be removed tomorrow and along with the
last barricade.
Metal plates will be installed over the gaps between the concrete
sections and wood deck sections of bridge 12 tomorrow too.
The last part of the project will be the concrete work at the Scott Blvd
parking lot that will not preclude trail users.
No comments:
Post a Comment