Today: Houf Construction is working their way out of the site and Roy Richardson & Son, Parks Recreation grading contractor is on the trail re-surfacing the trail from bridge #12 to the Scott Blvd trail access.
Tomorrow: Houf Construction will be removing their equipment and performing any last minute clean up tasks. Roy Richardson & Son, Parks Recreation grading contractor will be on the trail re-surfacing the trail from bridge #12 to the Scott Blvd trail access.
The trail section will remain closed until this weekend when the Parks & Recreation Department intends to have all the temporary gates and barriers removed and have the trail re-opened for all trail users.
Please do not enter the job site over the next few days. The site is a working job site and equipment operators are not always able to see trail users.
Tuesday, July 27, 2010
MKT Bridge #12 & #13 7-27-2010