Christensen Construction has made great progress on the tennis courts at Shepard School.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgeJDD6K7HF9L1cl-LLIk7kzDwwph1TLBJQ4kEiZ0ooTLL0xKHnM1z486pFLu9imU2TvZnWZEuwuA8-_J5d9f_8ESCc86mE8AT1wvFfUiqDmW9ftKszSYXbHkXW-iq1C3gENj6pCC1DW7lo/s320/IMG00200-20110831-0905.jpg)
The grading is complete, geo-fabric is placed and covered with 6" of gravel
prior to the asphalt surface.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjiS-kx-SphvKl6YAx-xpej2SVZl1jxD0Vk4SAPxTik6rzCqxu5zGKSENIVMoK5CJzWLdqZ6Y9PrBljZU3ocWLr7SOF_PRKzxf8rKscZHq2yIviA9X5yVcWGBz3tqo8KCgaI57e-XeoV536/s320/Shepard_tennis_grading_paving+%25284%2529.jpg)
The gravel is graded smooth, rolled and compacted, the slopes are checked for proper drainage, prior to asphalt paving.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjTxfdQdPJmn5Ldc9f9tH5TYmsff2iunFNQ_VFdMU8F3x3twik6AzlnA1aKe8RrNG8vUDAwsQrZ2L2T92jJISpc4Xfc62caLzlxqyfoikHXmJ_zuSTWtpaX1Oazsd1o3bfbprxLFuOMVoIa/s320/Shepard_tennis_grading_paving+%25285%2529.jpg)
The first layer of asphalt is complete. A second layer of finer asphalt goes down over this layer before fencing, net posts and paint coats.