MKT Bridge 12 & 13 Replacement Project Update 4-7-2010



The rain has come and gone, for the meantime. Forming and pouring will continue this afternoon and the west bank will be brought back to finished grade, around the piers. There have been questions about the terms used and at what locations work is taking place. Please see the rudimentary sketch, below, of what bridge #12 will look like.
With any luck next week the 'bridge section' will start to look more bridge-like, weather dependent. We only lost Monday, as a work day, so far this week so we hope we can progress in the muddy conditions.