MKT Bridge #12 & #13 7-20-2010...Rain Rain Go Away

Rain Rain Go Away....
Site remediation would still be in progress apart from the the almost 1.5 inches of rain that have fallen over the last few days. The area where Houf Construction needs to be is to the right of the bridge, approximately 6 feet under the water!

The rock from the temporary crossing will be used in the west approach to allow for an ADA trail compliant slope. Therefore, since the material is underwater, the job site operations are shut down temporarily.

The barrier to the East of the bridge is partially open for trail users to use the trail (at their own risk). Please use extreme caution and due care through this section of trail as 3" rock has been added to the rutted areas in preparation for resurfacing and is a very loose for trail surface.

We appreciate your understanding in these last few weeks of the project. We anticipate providing you with a much upgraded, safer bridge and a fresh new surface for the trail segment.