Tuesday, May 1, 2012

Maplewood Barn Update


The heavy rains over the weekend have put a temporary stop to the exterior work at the Barn. But the stage is done, all the subsurface drainage is installed, most of the conduit for the stage lights is installed, the light pole piers are installed and a lot of the sidewalks are in. Final painting (anything white will be painted to match the barn) and the installation of the window should happen this week.

Once the walks are complete, the conduit is finished and the poles installed, the sodding of the area immediately in front of the stage and seeding/strawing of the other areas can happen. 

Inside there's HVAC work going on. The Maplewood Community Theater has contracted with a plumber to do the fixture and finish plumbing work. And the group has started to load their theater materials in.

Dedication is in 16 days. But with a little luck and some dry weather it should be looking pretty good.

There are more photos of the construction at minus.com.