Thursday, May 20, 2010
MKT Bridge #12 - Temporary Crossing still flooded.....but not as much!
With all the rain over the last week, it has made it impossible for Houf Construction to reach the East bank to perform any work. The temporary Hinkson Crossing at Bridge #12 is still flooding with high water, though it appears, even with last nights rain to be receding.
Parks & Recreation staff will monitor the water level over the weekend to determine with Houf Construction when work will be able to continue on the bridge structure.
We are certainly hoping that this coming week's dry forecast will hold and that Houf Construction will be able to get to the East Hinkson bank to form and pour the end bent in order to set the steel truss section and concrete beams.
Pedaler's Jamboree Registrants stay tuned to this blog.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment