MKT Bridge 12 & 13 Replacement Project Update 3-17-2010

Wet conditions have hampered progress on Bridge #12, but today, equipment was running. Even with a muddy slippery site Houf Construction is forging ahead, forming the abutment for the west bank end bent wall and preparing to drive the steel pilings. Allstate Consultants performed a verification of markings, this morning, due to a design change from sheet steel piling bents to longer lasting concrete end bents adjusted field measurements. Looking forward to the 60 degree weather to dry out working conditions.