Despite having a few staff members home sick, we were able to get back on the trail today and nearly complete the MKT. Here's an update:

MKT: New holes at bridge #1 & 8 repaired. Final trail surface mix has been spread, rolled and compacted. Trail is essentially repaired although additional rock is needed along shoulder in one particular area. However, this shouldn't impact any trail users.

Bear Creek Trail: Began adding 1" roll stone along washouts from Creasey Springs Trailhead entrance heading west toward Cosmos Park. Anticipate a few more days and this trail will be repaired and staff will be able to get to the Hinkson Creek Trail.