Tuesday, December 13, 2011

Scotts Branch Trail

The 8' wide concrete trail from Rollins to Weaver has been completed. We will begin back filling the trail with soil, placing straw mulch and spreading winter wheat for erosion control as soon as the weather allows.

Wednesday, November 16, 2011

Scotts Branch Trail

Work has begun on the first part of the Scotts Branch Trail. We are starting at Weaver St. and working our way back to Rollins Road with the 8' wide concrete trail.


Approximately 1/3 of the trail from Weaver to Rollins is completed. We have some grading and culvert pipe work to do and then, weather permitting, we should be able to complete the section from Weaver St. to Rollins Road by Dec. 1, 2011. Finish grading work, seeding and straw work will be ongoing into the Spring.