Friday, June 4, 2010

Smiley Lane Park -Cul-de-Sac 6-4-2010


Stockman Construction was back on site yesterday, 6-3-2010, to pour 50+% of the sidewalk around the Cul-de-Sac. Next step of the park development is to tie the trail and concrete walks from shelter and playground to the sidewalk. Also a drinking fountain will be installed in near proximity to the shelter and playground. One of the last steps after the previous items are taken care of is installing and planting the bio-swale and rain garden system.

A C.A.R.P. planting will take place June 12th and the detention pond at the North end of the Park. This will be down to prepare the environment for fish stocking that will take place either this fall or following Spring

Monday, May 3, 2010

Smiley Lane Park -Cul-de-Sac 5-7-2010

Stockman Construction is well on their way to completing the Cul-De-Sac for the park. Sidewalks around the cul-de-sac will be installed next week, weather permitting. P&R Construction crews will then finish connecting sidewalks to the shelter and the playground and our Forestry division will finish up the gravel trail.
The last feature of the park will be the bio-swale and rain garden system that will treat and release the storm water produced from the cul-de-sac, shelter and play field.

Thursday, April 29, 2010

Smiley Lane Park


The first section of the Cul-de-Sac has been poured by Stockman Construction. Work will progress through Friday as weather allows. Approximate completion in two weeks, weather dependent.