Friday, May 7, 2010

MKT Bridge #12 - Work Continues 5-7-2010

Houf Construction finished the last of the three piers this week and drove pilings yesterday and today for the second of two Abutments. The abutment will be formed and poured next week if the predicted rain does not rain us out.
The bypass for bridge #12 and #13 are both passable, but please use caution as the surface is uneven and the tread material loose. The barricades have been set to the side for your continued trail enjoyment over the weekend, morning and evening hours.